The county will be repairing Main Street in Metamora on the south side of the canal from about Aug 17 through Aug 28. All work should be complete by August 28. The first week it is anticipated they will do the work on the east side of Columbia Street, and the second week on the west side of Columbia. Traffic will obviously be impacted during the work, but sidewalk access will always be available to all shops.
This road work should dramatically help the problems of drainage forcing our town visitors to walk down the middle of the street and threats from icing of pooled water, plus stopping much of the storm water entering building basements because the streets are too high.
Please be patient- it will be an inconvenience, but only for a short time.
Thank you.